What is Cosmec Inc.’s standard lead-time for the manufacture of bearings?
The lead-time varies depending on the type and quantity of bearings required. Bearings requiring designing as well as the production of shop drawings typically require between 6 and 10 weeks for design and drafting. Production and delivery of these bearings is typically 12 to 14 weeks after the receipt of approved design calculations and approved shop drawings. Bearings that do not require designing can typically take much less time in both producing shop drawings and in production. Job-specific lead-times, however, can be accommodated. Please contact your Salesperson to discuss your specific lead-time requirements.